Architecture (Seaton Hall Expansion & Renovation)
Key Dates:
Schematic design complete: 12/3/2014
Construction manager interviews: 2/27/2015
Design development compete: 3/4/2015
50% construction documents: 5/20/2015
Construction documents complete: 8/5/2015
Approximate construction schedule: begin 9/2015; complete 6/2017
Construction manager interviews: 2/27/2015
Design development compete: 3/4/2015
50% construction documents: 5/20/2015
Construction documents complete: 8/5/2015
Approximate construction schedule: begin 9/2015; complete 6/2017